How long does it take to renovate a kitchen in Sydney? A like-for-like kitchen renovation usually takes 6 to 10 weeks on site, and a layout change that removes a wall takes 10 to 16 weeks. Those weeks begin only after 4 to 12 weeks of design, approvals and ordering, so the real answer is decided mostly before demolition day. This guide is for Sydney homeowners planning a significant kitchen renovation who want a realistic start-to-finish picture. The ranges come from the timelines Trade Industries Group (TIG) publishes for its own projects.
Key Takeaways
- Plan for 6 to 10 weeks on site for a like-for-like layout and 10 to 16 weeks if walls move, then add the pre-site phase.
- Ask for the confirmed cabinetry delivery date before you agree on a demolition date.
- Lock layout, appliances and finishes before ordering, because changes after that point can restart the supply timeline.
- Check approvals early. TIG’s indicative allowances are about 10 to 20 business days for a Complying Development Certificate and 40 to 90 days for a council Development Application. These are not guaranteed timeframes.
- Ask any builder for a written programme that lists dates for joinery, stone and appliances.
- Choose your start date last, once design, approvals and deliveries are confirmed.
How Long Does a Kitchen Renovation Take in Sydney?
A standard kitchen renovation that keeps the existing layout takes 6 to 10 weeks on site, from demolition to handover. A renovation that removes walls or changes the layout takes 10 to 16 weeks.
| Kitchen project type | Before site starts | On site (demolition to handover) |
| Like-for-like layout | 4 to 12 weeks | 6 to 10 weeks |
| Layout change with wall removal | 4 to 12 weeks, longer if approval is needed | 10 to 16 weeks |
These are planning ranges taken from TIG’s published renovation timelines, not guarantees. “Before site starts” covers design, approvals and ordering. For the whole-home picture, including bathrooms and laundries, see how long a whole-home renovation takes in Sydney.
How Do Planning, Ordering and Construction Affect Your Kitchen Renovation Timeline?
A kitchen renovation moves through three phases: planning, ordering and construction. Homeowners usually see only the construction phase, which is why a “six-week kitchen” can mean a much longer wait from first conversation to first meal. Some activities can overlap, but each phase depends on the one before it.
- Planning: layout, finishes, appliance choices and any approvals. Confirm the relevant design details and specifications before placing orders.
- Ordering: cabinetry, stone benchtops and appliances. Cabinets are built to the final layout, so ordering follows planning. Once the design is confirmed, the delivery wait can often run alongside approvals and other preparation. Semi-custom cabinetry typically has a 3 to 5 week lead time, bespoke joinery can take up to 12 weeks, and imported appliances can take 4 to 12 weeks. Stone is the exception. The benchtop is measured only after the cabinets are installed, so its fabrication cannot start early.
- Construction: demolition through to handover, the 6 to 16 weeks shown above. It starts once planning is complete, approvals are in place and cabinetry delivery is confirmed.
Planning comes first because it decides what is ordered and approved. Ordering and approvals can overlap in some cases, but construction depends on both, and a kitchen cannot finish earlier than its slowest dependency allows.
What Are the Stages of a Kitchen Renovation, in Order?
A kitchen renovation that keeps the existing layout moves through six on-site stages. The order matters because each trade depends on the one before it.
- Demolition and strip-out. The old kitchen comes out and the room is cleared and protected.
- Rough-in. Plumbing and electrical lines are moved or added, and walls, ceilings and floors are repaired and prepared.
- Cabinet installation. On a typical program this falls around days 14 to 28 of site work, counted in calendar days.
- Benchtop templating and fabrication. The stonemason measures the benchtop only after the cabinets are in, fabricates it over 2 to 3 weeks, then returns to install it.
- Splash back, painting and tiling. Finishing trades close up the room.
- Appliance fit-off and handover. Final fit-off falls around days 42 to 60 of site work on a standard programme, followed by quality checks before handover.
Stage 4 is the hardest stretch for households staying at home, because the sink and benchtop are missing while the stone is made. Our guide to living at home during a renovation covers temporary kitchens, dust and noise.
If your kitchen involves removing a wall, structural work comes before the rough-in stage. Where the wall is load-bearing, this usually involves an engineer’s design, new support or framing, and any inspections the certifier requires before walls and ceilings are closed up. Ask TIG to show exactly where each of these sits in your program and whether it is already included in the 10 to 16 week on-site range.
Why Does Ordering Cabinetry Before Demolition Matter So Much?
Joinery lead times can significantly affect how long a kitchen renovation takes. Starting demolition without a coordinated cabinetry schedule increases the risk of delays. Semi-custom cabinetry typically takes 3 to 5 weeks to arrive, and bespoke joinery can take up to 12 weeks, based on TIG’s published lead times.
Cabinets are built to the final measure and layout, so layout and appliance choices need to be locked before the order goes in. In our view, a practical rule follows from that: ask for the confirmed cabinetry delivery date before you agree on a demolition date. If the delivery date is not confirmed, the finish date is not confirmed either.
What Makes a Sydney Kitchen Renovation Take Longer?
Six factors can add time to a Sydney kitchen renovation. Some affect approvals, some affect ordering and some affect construction, so they cannot simply be added together. The figures below come from TIG’s published timelines and are indicative allowances.
| Factor | Typical added time | Mainly affects |
| Removing a wall for an open-plan layout | 2 to 5 weeks | Approvals and construction |
| Adding a butler’s pantry | 3 to 5 weeks | Construction and ordering |
| Heritage property | 1 to 3 weeks | Approvals |
| Apartment kitchen (strata approval buffer) | 2 to 4 weeks | Approvals |
| Suspected asbestos (testing, clearance, licensed removal) | At least 2 to 4 weeks | Construction |
| Imported appliances | Lead time of 4 to 12 weeks, so order early | Ordering |
A single “average kitchen timeline” can mislead, so ask any builder which of these apply to your home and whether each one affects approvals, ordering or construction.
Does a Kitchen Renovation Need Council Approval in NSW?
Whether a kitchen renovation needs approval depends on the work, not the room. Replacing cabinets and fixtures in the same position is treated differently from removing a load-bearing wall or altering a heritage property, which can add weeks or months. Whether minor internal work is exempt from approval depends on the proposed work and the development standards that apply to your property, so confirm this with your council or certifier before assuming no approval is needed.
TIG’s published timelines put a Complying Development Certificate through a private certifier at about 10 to 20 business days, and a standard Development Application with council at 40 to 90 days in Sydney, with heritage adding more. Treat these as indicative allowances to confirm for your project, not guaranteed completion windows. If your project goes through a Development Application, a construction certificate is also required before building work starts, so a lodged or approved application alone does not complete the approval process. Applications are lodged online through the NSW Planning Portal.
How Can You Keep a Kitchen Renovation on Schedule?
Late decisions and deliveries can cause avoidable delays. These habits protect the program:
- Confirm which selections must be finalized before signing, and the deadlines for any outstanding choices.
- Confirm appliance specifications before cabinetry is ordered. Cutouts and clearances are built around the exact appliance.
- Get delivery dates in writing for joinery, stone and appliances.
- Record every change in writing. A contract should state how variations are priced and how they affect the program. Read what to check before you sign a fixed price renovation contract before you commit.
- Set up a temporary kitchen before demolition day, not after the sink is gone.
Final Thoughts: How Long Does It Take to Renovate a Kitchen?
So, how long does it take to renovate a kitchen in Sydney? Usually 6 to 10 weeks on site for a like-for-like layout and 10 to 16 weeks if walls move, after 4 to 12 weeks of design, approvals and ordering. These are planning ranges, not guarantees, and the real answer for your home is settled mostly before demolition day.
The best way to keep your kitchen on schedule is to confirm the things that hold up the start: your design details, your approvals and your cabinetry delivery date. Choose your start date last, ask for a written program, and set up a temporary kitchen before the old one comes out.
Get a Realistic Program for Your Kitchen
Every kitchen has its own timeline. Your layout, your approvals and your cabinetry lead times decide how long the project really takes, and a builder should be able to show you that before you sign anything.
Talk through your plans with the TIG team and we will look at what is involved in your kitchen, which approvals may apply and when orders need to be placed, so you know what to expect from first conversation to handover. It is an informal conversation with no obligation and no pressure. See What’s Possible for My Space or call Trent’s team on 0468 013 922, Monday to Saturday, 8:00 am to 5:00 pm.
Frequently Asked Questions
1. How long will I be without a usable kitchen?
From demolition day until final appliance fit-off, which falls around days 42 to 60 of site work on a standard program. A kitchen that keeps its layout takes 6 to 10 weeks on site, and one that removes a wall takes 10 to 16 weeks. The hardest stretch is while the stone benchtop is made, which takes 2 to 3 weeks after the cabinets are installed, so plan a temporary kitchen before demolition day.
2. Can I stay at home during a kitchen renovation?
Many households do, with a temporary kitchen set up elsewhere in the home. Dust, noise and the weeks without a sink make it harder, so decide before you sign.
3. When should I order cabinetry and appliances?
Once your layout, appliance models and finishes are confirmed, and before demolition begins. Semi-custom cabinetry typically takes 3 to 5 weeks, bespoke joinery up to 12 weeks and imported appliances 4 to 12 weeks, based on TIG’s published lead times. Ask for confirmed delivery dates in writing before you agree on a demolition date.
4. Does an apartment kitchen renovation take longer?
Often yes, because of strata approval. A committee can approve minor renovations where your scheme’s by-laws authorize it, and TIG allows about 2 to 4 weeks. Major renovations need a special resolution of the owners corporation, and TIG allows 6 to 12 weeks. Check your by-laws early and confirm the timing with your strata manager.
5. What happens if the agreed program changes?
That depends on your contract. Before signing, ask what the program includes, what counts as a delay, how variations are recorded and priced, and how each change affects the finish date.
6. How long does it take to renovate a kitchen from first conversation to handover?
In Sydney, about 4 to 12 weeks of design, approvals and ordering, followed by 6 to 10 weeks on site for a like-for-like layout or 10 to 16 weeks if walls move. Cabinetry delivery, approvals and the age of your home decide when work can really start. Confirm those first, and your kitchen is far more likely to finish when planned.